How to complete the G703 — with a free G702/G703-style template

This guide and template are free. They're published by Goodfolk, which is measuring interest in a possible progress-billing tool for subcontractors — you can read about the concept and tell us whether it's worth building.

The G703 continuation sheet, column by column

The continuation sheet is where the real work happens: one row per line of your schedule of values.

  • AItem No.. The line number for each piece of work, matching your schedule of values.
  • BDescription of Work. What the line covers — for example "Rough-in, 2nd floor" or "Switchgear, material".
  • CScheduled Value. The dollar amount assigned to this line in your schedule of values. All lines together equal the contract sum to date.
  • DWork Completed — From Previous Application. The total billed on this line in all earlier applications. Copy it from last month's column G (minus stored materials since installed, if your GC tracks them that way).
  • EWork Completed — This Period. The value of work put in place on this line since the last application.
  • FMaterials and Equipment Suitably Stored. The value of materials delivered and stored but not yet installed, where your contract allows billing for them.
  • GTotal Completed and Stored to Date. Previous + This Period + Stored (D + E + F).
  • G/C%. Total Completed and Stored ÷ Scheduled Value (G ÷ C).
  • HBalance to Finish. Scheduled Value − Total Completed and Stored (C − G).
  • IRetainage. The retainage percentage in your contract, applied to Total Completed and Stored (G × retainage %).

The G702 summary, line by line

The summary page rolls the continuation sheet up into the amount you're asking to be paid.

  1. 01Original Contract Sum. The contract amount as signed.
  2. 02Net Change by Change Orders. The total of all approved change orders, added or deducted.
  3. 03Contract Sum to Date. Original Contract Sum + Net Change by Change Orders.
  4. 04Total Completed and Stored to Date. The column G total from the G703.
  5. 05Retainage. The column I total from the G703.
  6. 06Total Earned Less Retainage. Total Completed and Stored to Date − Retainage.
  7. 07Less Previous Certificates for Payment. What you were certified for in earlier applications (the previous application's Total Earned Less Retainage).
  8. 08Current Payment Due. Total Earned Less Retainage − Less Previous Certificates for Payment.
  9. 09Balance to Finish, Including Retainage. Contract Sum to Date − Total Completed and Stored to Date.

Get the template

Two sheets — a G703-style continuation sheet with 15 item rows and a G702-style summary — with the arithmetic above already built in. Set your retainage percentage at the top (it starts at 10).