The G703 continuation sheet, column by column
The continuation sheet is where the real work happens: one row per line of your schedule of values.
- AItem No.. The line number for each piece of work, matching your schedule of values.
- BDescription of Work. What the line covers — for example "Rough-in, 2nd floor" or "Switchgear, material".
- CScheduled Value. The dollar amount assigned to this line in your schedule of values. All lines together equal the contract sum to date.
- DWork Completed — From Previous Application. The total billed on this line in all earlier applications. Copy it from last month's column G (minus stored materials since installed, if your GC tracks them that way).
- EWork Completed — This Period. The value of work put in place on this line since the last application.
- FMaterials and Equipment Suitably Stored. The value of materials delivered and stored but not yet installed, where your contract allows billing for them.
- GTotal Completed and Stored to Date. Previous + This Period + Stored (D + E + F).
- G/C%. Total Completed and Stored ÷ Scheduled Value (G ÷ C).
- HBalance to Finish. Scheduled Value − Total Completed and Stored (C − G).
- IRetainage. The retainage percentage in your contract, applied to Total Completed and Stored (G × retainage %).
The G702 summary, line by line
The summary page rolls the continuation sheet up into the amount you're asking to be paid.
- 01Original Contract Sum. The contract amount as signed.
- 02Net Change by Change Orders. The total of all approved change orders, added or deducted.
- 03Contract Sum to Date. Original Contract Sum + Net Change by Change Orders.
- 04Total Completed and Stored to Date. The column G total from the G703.
- 05Retainage. The column I total from the G703.
- 06Total Earned Less Retainage. Total Completed and Stored to Date − Retainage.
- 07Less Previous Certificates for Payment. What you were certified for in earlier applications (the previous application's Total Earned Less Retainage).
- 08Current Payment Due. Total Earned Less Retainage − Less Previous Certificates for Payment.
- 09Balance to Finish, Including Retainage. Contract Sum to Date − Total Completed and Stored to Date.